Refer: https://docs.microsoft.com/en-us/vsts/work/work-items/guidance/cmmi-process-workflow
Showing posts with label Microsoft Team Foundation. Show all posts
Showing posts with label Microsoft Team Foundation. Show all posts
Wednesday, 3 January 2018
Friday, 22 December 2017
Team Foundation_1.CMMI Process
I use Microsoft Team Foundation as a tool for tracking Requirement, Change Request, Issue and Risk. It like JIRA.
I choose CMMI process to manage projects because CMMI is fine for manage detail and attach documents. Also, I can propose CMMI project management to understand and work together.
Refer https://docs.microsoft.com/en-us/vsts/work/work-items/guidance/choose-process
I choose CMMI process to manage projects because CMMI is fine for manage detail and attach documents. Also, I can propose CMMI project management to understand and work together.
CMMI Process.
CMMI Status in Microsoft Team Foundation.
Test process.
Refer https://docs.microsoft.com/en-us/vsts/work/work-items/guidance/choose-process
Friday, 15 December 2017
Team Foundation_2.Dash board
Project dashboard.
From my example, I can design a dashboard to see project's overview as I want to monitor in part of software development project.
I can track open requirements and active bugs by sprint.
Also, I can track all requirements, issues and risks.
Benefit:
- Easy for monitoring.
- It is the good report for presentation to my client and my upper management level.
- I send this report to my client by biweekly.
- I send this report to my management level by weekly.
If a project is an urgent schedule or critical, I will send this report 2 times a week. - If I want to see detail, I can click the hyperlink.
- It can show graph, summary and counting number of your interesting area.
Incidents.
From my example, I can design dashboard of maintenance project by yearly and monthly.
Benefit:
- Easy for monitoring.
- It is the good report for presentation to my customer and my upper management level.
- I send this report to my client by monthly.
- I send this report to my management level by monthly. If any incidents are urgent or critical, I will send at properly time. - If I want to see detail, I can click the hyperlink.
- It can show graph, summary and counting number of your interesting area.